The project consists of street reconstruction of Front Street, from Bough Street to Chestnut Street and Second Street from Bough Street to Raspberry Alley in the Isle of Que.
Performance Performance Measures:
Job Creation Measures
Number of FTEs created/retained:
1st Q 2010: 0.00 2nd Q 2010: 0.00 3rd Q 2010: 0.00 4th Q 2010: 0.00
1st Q 2011: 0.00
Economic Growth Measures
Cumulative Expenditures to date: $33,470 (may incl. expenditures from two quarters in 2009)
Dollars Expended on Road/Street/Sidewalk Projects:
1st Q 2010: $33,470 2nd Q 2010: $0 3rd Q 2010: $0 4th Q 2010: $0
1st Q 2011: $0
Percentage of Project Completed: 100%