ADA Ramps Phila Ph 2(C)
Construction of ADA Curb Ramps in various locations of Philadelphia County
Project Status 51%
Counties
Municipalities
Philadelphia
Project Schedule
Construction Start Date
2009-08-17
Estimated Complete Date
2009-10-30
Estimated Total Funding Amount
$1,605,428
Funding Recipient(s)
James J. Anderson Construction Company, Inc.
Amount:
$1,433,418 (ARRA)
Sub-Recipient(s)
Armour & Sons Electric, Inc.
Peggy Grant d/b/a T & G Construction Co.
McMahon Associates, Inc.
Zone Striping, Inc.
Inspection
Trc Engineers, Inc.
Amount:
$120,966 (ARRA)
Estimated Jobs Created/Retained
32